Photo: ,
Diary Correspondent
Partial gas supplies have resumed to
the national grid from the damaged floating LNG terminal in Maheshkhali, but
the development has yet to bring significant relief to the power sector.
Residents in several areas are experiencing load shedding both during the day
and late at night, with the electricity shortfall reaching between 2,000 and
nearly 3,000 megawatts in parts of the country on Saturday.
According to officials in the power
sector, electricity demand stood at 18,896MW at 5pm on Saturday, when 2,534MW
of load shedding was required to manage the shortfall. Two hours earlier, at
3pm, demand was 15,377MW while load shedding stood at 2,958MW.
The situation was also strained in
the morning, when demand is normally lower. At 9am, against demand of 13,739MW,
authorities had to impose 1,505MW of load shedding.
The most concerning development has
been the power shortage during the early hours of the night. At 3am on Friday,
demand stood at 14,407MW, while 2,432MW of load shedding was recorded. This
indicates that the supply deficit is not limited to peak daytime hours.
The situation had been relatively
stable on Thursday, when load shedding remained between 300MW and 400MW.
However, the power situation deteriorated sharply within a day.
Gas Shortage Hits Power Generation
Power sector officials said reduced
gas supplies have prevented gas-fired power plants from operating at their
required capacity. Gas supplies to power plants, which previously stood at
around 990 to 1,000 million cubic feet per day, have now fallen to roughly 680
million cubic feet.
Meanwhile, one unit of the Payra
power plant remains out of operation, further reducing electricity generation.
The plant is currently generating around 400MW to 500MW, according to
officials.
LNG Supply Resumes
Gas supplies from the damaged
floating LNG terminal in Maheshkhali resumed to the national grid at 3:10am on
Thursday. The terminal is currently supplying around 280 million cubic feet of
gas per day.
Officials hope that once the second
boiler is brought back into operation, another 300 million cubic feet could be
added to the national grid, potentially improving the overall gas supply
situation.
Petrobangla Chairman Md Abdul Mannan
said gas supplies would return to normal once the terminal becomes fully operational.
He also said the necessary LNG cargoes had been secured.
Supply Rises but Shortfall Remains Significant
Before the fire at the Maheshkhali
terminal on July 21, around 2.65 billion cubic feet of gas was supplied to the
national grid every day. Following the incident, supply fell to around 2.12
billion cubic feet.
It has since increased to
approximately 2.367 billion cubic feet. However, with daily national gas demand
estimated at around 3.8 billion cubic feet, a substantial gap between demand
and supply remains.
As a result, the partial resumption
of gas supplies from the LNG terminal has yet to translate into significant
relief in electricity generation. Until gas supplies return to normal,
uncertainty will remain over when the country can expect relief from the
ongoing power shortage and load shedding.